File #: 18-013    Version: 1 Name: Park Operations Facility Discussion
Type: Report Status: Agenda Ready
File created: 1/2/2018 In control: City Commission
On agenda: 1/9/2018 Final action:
Title: Park Operations Facility Discussion
Sponsors: Phil Lewis
Indexes: Goal 2: Address Critical Facility Needs.
Attachments: 1. Staff Report, 2. Cost Estimate Memo, 3. Park Operations Site Plan
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Park Operations Facility Discussion

Body
RECOMMENDED ACTION (Motion):
Staff recommends the City Commission provide direction for next steps.

BACKGROUND:
The Parks/Cemetery Shops have been red tagged since 2013 due to several main structural component failures, rotten siding, window framing failures, chimney structure failure, and the safety factors and liability of load and people within the building. This building was part of the existing residence from the family tending the Cemetery and was constructed in the 1950’s. Staff has used a mobile rental unit for the last four years.

At the April 11, 2017 Commission Work Session, staff presented a concept that would suffice for existing staff and seasonal staff with limited shop space. The proposal did not have considerations for future staffing or equipment needs. After discussing the original concept design, the Commission asked staff to bring back additional concepts that showed 1/3 - 1/2 again more space and a proposal that would be for a 20 to 50 year concept design.

Staff worked with LRS Architects to develop the requested concept designs. Staff presented concept designs for discussion at the October 10, 2017 Commission Work Session. The concepts showed an incrementally increased size of the building and associated parking. In consideration of the financial capacity to build in total, phasing of the concepts was integral to the design process. Commission gave direction for staff to move forward with Option B (attached) and asked if additional phasing might be possible. LRS Architects have provided an additional cost estimate for a three phase construction plan (attached). Total costs of constructing Phase 1, including direct construction costs and soft costs, are estimated at $1,300,000.

Through the FY2017-19 budget process, Commission dedicated $650,000 in general funds for construction of the Parks Operations Facility. Staff have evaluated budget allocations for the current budget bi...

Click here for full text